Digital Access

Digital Access
Access saukvalley.com from all your digital devices and receive breaking news and updates from around the area.

Home Delivery

Home Delivery
Local news, prep sports, Chicago sports, local and regional entertainment, business, home and lifestyle, food, classified and more! News you use every day! Daily, Daily including the e-Edition or e-Edition only.

Text Alerts

Text Alerts
Choose your news! Select the text alerts you want to receive: breaking news, prep sports scores, school closings, weather, and more. Text alerts are a free service from SaukValley.com, but text rates may apply.

Email Newsletters

Email Newsletters
We'll deliver news & updates to your inbox. Sign up for free e-newsletters today.
The Holiday Gift Auction is Live! Click here and bid now on great local gifts!
Local

Zoning panel: No wind farm

Project would include Whiteside, Lee counties

PRINCETON – The Bureau County zoning board is recommending against a company’s proposed wind farm.

The Bureau County Board has the final say.

On Tuesday, the Zoning Board of Appeals unanimously rejected all 19 of Mainstream Renewable Power’s planned turbines. They were a part of a wind farm that would include nine turbines in Whiteside County and 53 in Lee County.

During the summer, the Whiteside County Board approved the nine turbines, with two also needing the village of Deer Grove’s approval.

Lee County has been holding public hearings on Mainstream’s plan since July.

The Bureau County zoning board’s process was exhaustive. It met 21 times since March on Mainstream’s proposal.

Before that, the county revised its wind energy ordinance. Mainstream’s wind farm was the first test.

“The members felt a strong obligation to follow the ordinance,” member Barry Welbers said. “They did follow it stringently. Whether it’s the most perfect ordinance, that remains to be seen.”

Welbers said he voted down the turbines because the company’s plan didn’t comply with the ordinance.

For instance, he said, the decommissioning plan, in the event of the turbines’ abandonment, was inadequate.

Also, Mainstream didn’t provide a road-use agreement, which the ordinance required, Welbers said.

“Their argument was that they were township roads,” Welbers said, adding that he didn’t think that made a difference.

Mainstream’s Matt Boss said his company would get the deliberation transcripts in the next few days to better understand the zoning board’s reasoning.

“We had a good project yesterday; we have a good project today,” he said.

Rick Porter, who represented residents against the wind farm, said he hoped the County Board put a lot of weight in the zoning board’s recommendation. County Board members rarely attend zoning board meetings, he said.

“The Bureau County Zoning Board of Appeals was very attentive. They were vested in the process. They spent a lot of time understanding the issues,” he said.

The County Board has rejected the zoning panel’s advice before. Last year, the County Board extended the permits for the proposed Walnut Ridge wind farm, contrary to the zoning board’s recommendation.

On Tuesday, the County Board’s Planning and Zoning Committee is expected to make its own recommendation on the Mainstream proposal. The County Board will decide on Dec. 11.

To attend

The Bureau County Board's Planning and Zoning Committee will make a recommendation on Mainstream Renewable Power's wind farm proposal during its meeting at 5:30 p.m. Tuesday at the County Courthouse, 700 S. Main St. in Princeton.

The Bureau County Board is expected to make a final decision at its meeting at 6:30 p.m. Dec. 11, also at the courthouse.

Call Kris Donarski, the county's zoning officer, at 815-875-2077 for more information.