Connection restored

Bridge finished a month early; contractor to reap $1M bonus

Text Size: AaAaAaAaAa
Crews prepare the First Avenue Bridge for lane stripping Monday afternoon. After the final stripes were painted, the bridge was opened from two lanes to four. Crews will finish the final cleanup this morning. The bridge must be done by midnight Wednesday for the contractor, Civil Constructors, to collect a $1 million bonus, a deadline it will meet "barring any unforeseen issues," Illinois Department of Transportation project engineer Matt Hardt said. (Philip Marruffo/pmarruffo@saukva)
Buy Sauk Valley Media Photos »

STERLING – Work to rebuild the main artery connecting Sterling and Rock Falls is being completed a month ahead of schedule.

Freeport-based Civil Constructors began work on the $27 million First Avenue Bridge project in mid-January. Monday, crews painted the final stripes on the road, and the bridge was opened from two lanes to four.

The deadline to complete the project is Nov. 16. Each day saved earns the contractor an extra $33,333, up to 30 days, for a total of $1 million.

The bridge must be done by midnight Wednesday for Civil to collect the full bonus, a deadline it will meet “barring any unforeseen issues,” Illinois Department of Transportation project engineer Matt Hardt said.

Crews are to finish the final cleanup work under the bridge this morning. A ribbon-cutting will be at 11 a.m. Nov. 7, at a spot to be determined, Hardt said.

“Start to finish, everything went better than expected,” he said. “We didn’t have any major delays, there was a few fairly good-sized design changes, but all in all, everything went well. The weather was good, good contractor.”

The bridge, which carries 27,000 vehicles a day, needed its substructure replaced. It was built in the early 1920s, and its last major rehab was done in 1980-81, Hardt said.

The project was awarded in December and work began a month later, he said.

“That’s a real short time for the contractor to get everything in line from different contractors to materials. Civil did an outstanding job of making sure everything was on the job when it was needed.”

Projects of this scope usually take 2 years, but “the reason it was done in 1 year is because it was the main artery between Sterling and Rock Falls,” he said.

Construction crews have been working 72 hours a week; for 6 of the 9 months, they worked around the clock, he said.

“What a lot of people may not realize .. we give [Civil] a million-dollar bonus, but it isn’t really a million dollars in their pocket because they had to spend money to make the money – all the overtime and everything else involved,” Hardt said.

Previous Page|1||

Comments

Blogs

» Extra! Extra! - A blog by Chris Heimerman
Extra! Extra! - A blog by Chris Heimerman

Knowledge is power, right?

Bryan Frederick is a Lifestyle Medicine Instructor at CGH Medical Center, and he's got me thinking and re-thinking my approach to weight loss.
» Out Here
Out Here

Why the need for middleman?

The other day, we ran a story about the Dixon Tourism Board's website, which is hard to navigate and missing key information, particularly about the Petunia Festival. Are we wasting our time examining local tourism websites?

Reader Poll

Have you ever gone boating on the Rock River?

Yes
No