Connection restored
Bridge finished a month early; contractor to reap $1M bonus
STERLING – Work to rebuild the main artery connecting Sterling and Rock Falls is being completed a month ahead of schedule.
Freeport-based Civil Constructors began work on the $27 million First Avenue Bridge project in mid-January. Monday, crews painted the final stripes on the road, and the bridge was opened from two lanes to four.
The deadline to complete the project is Nov. 16. Each day saved earns the contractor an extra $33,333, up to 30 days, for a total of $1 million.
Story Archived
Only the most recent 7 days of articles are available for free. For articles older than 7 days there is a small fee for retrieval from our archive. If you are a registered member of the site, the content is free just by signing in below.
Please sign in with your Comment Member ID and password.
Purchase Access
To allow for flexibility, we offer a variety of options for purchasing articles:
Having trouble?
If you have any technical difficulties, either with your username and password or with the payment options, please contact us by e-mail at archivedesk@shawmedia.com