Stage 2 demolition complete, IDOT says
Project on schedule for fall completion
STERLING – Stage 2 demolition of the $27 million First Avenue Bridge project is done, and crews have started excavating rock for the new pier footings, project engineer Matt Hardt said Monday.
The footing was poured for pier 1 on Saturday. (The piers are labeled one through seven as they go from Rock Falls to Sterling.)
Work has begun on the south abutment, and road work has begun on the north and south sides. Northwest Illinois Construction Co. is pouring new concrete pavement later this week, Hardt said.
Story Archived
Only the most recent 7 days of articles are available for free. For articles older than 7 days there is a small fee for retrieval from our archive. If you are a registered member of the site, the content is free just by signing in below.
Please sign in with your Comment Member ID and password.
Purchase Access
To allow for flexibility, we offer a variety of options for purchasing articles:
Having trouble?
If you have any technical difficulties, either with your username and password or with the payment options, please contact us by e-mail at archivedesk@shawmedia.com