Building costs rise at US nuclear sites

ATLANTA (AP) — America's first new nuclear plants in more than a decade are costing billions more to build and sometimes taking longer to deliver than planned, problems that could chill the industry's hopes for a jumpstart to the nation's new nuclear age.

Licensing delay charges, soaring construction expenses and installation glitches as mundane as misshapen metal bars have driven up the costs of three plants in Georgia, Tennessee and South Carolina, from hundreds of millions to as much as $2 billion, according to an Associated Press analysis of public records and regulatory filings.

Those problems, along with jangled nerves from last year's meltdown in Japan and the lure of cheap natural gas, could discourage utilities from sinking cash into new reactors, experts said. The building slowdown would be another blow to the so-called nuclear renaissance, a drive over the past decade to build 30 new reactors to meet the country's growing power needs. Industry watchers now say that only a handful will be built this decade.

Story Archived

Only the most recent 7 days of articles are available for free. For articles older than 7 days there is a small fee for retrieval from our archive. If you are a registered member of the site, the content is free just by signing in below.

Please sign in with your Comment Member ID and password.

Did you purchase access?

Member ID:
Password:
Forgot Your Password?
Register to comment.

Purchase Access
To allow for flexibility, we offer a variety of options for purchasing articles:
Purchase options


Having trouble?

If you have any technical difficulties, either with your username and password or with the payment options, please contact us by e-mail at archivedesk@shawmedia.com

Blogs

» Extra! Extra! - A blog by Chris Heimerman
Extra! Extra! - A blog by Chris Heimerman

Knowledge is power, right?

Bryan Frederick is a Lifestyle Medicine Instructor at CGH Medical Center, and he's got me thinking and re-thinking my approach to weight loss.
» Out Here
Out Here

Why the need for middleman?

The other day, we ran a story about the Dixon Tourism Board's website, which is hard to navigate and missing key information, particularly about the Petunia Festival. Are we wasting our time examining local tourism websites?

Reader Poll

Have you ever gone boating on the Rock River?

Yes
No